ELECTRICAL & INSTRUMENTS WORKS FOR 2 CPU UNITS PROJECT

ELECTRICAL & INSTRUMENTS WORKS FOR 2 CPU UNITS PROJECT

Project Overview

Our Role

E & I Subcontractor

End User

VTTI Fujairah Terminal

Job Carried Out

Installation, Testing & Commissioning Support for Electrical & Instrumentation

Project Description

The project was to set up 02 Nos. of Crude Processing Units (CPU1 & CPU2) inside of the VTTI Fujairah Terminal. All the Equipment, Instruments, and Materials were provided by M/s BURANDO and Metromac has carried out the complete construction for the E&I works including the final Documentation. The Engineering Contractor is BURANDO.

Scope of Work
  • Installation of all Instruments & it's tubing

  • Laying of all-new Power, Control, and Signal Cables

  • Cable Glanding & Termination, Installation of Light Fixtures

  • Installation of Gas/Flame Detectors and FM200 System

  • Electrical Cable Laying and Termination Activities for the HVAC Units & New Transformer

  • Removal of existing transformer and Supply with Installation of New Transformer (200KVA)

  • Installation of LT panels for Primary and Secondary along with Transformer.

  • Commissioning the Transformer

  • Troubleshooting and Maintenance works